The transformation of Byford to a harness training centre of excellence centre is well underway with a number of preliminary works now completed.
Improvements undertaken to date include:
The drainage works in particular have significantly improved the performance of the main track, especially throughout the winter period.
The next phase of Stage 1 Redevelopment Works will commence on Monday, 4 January 2010 and will last for approximately four weeks. The works will encompass the following;
The works will greatly enhance the comfort of track users when using the respective stalls whilst the construction of the new maintenance road (and future relocation of machinery compound) will significantly reduce current horse / machinery conflict issues.
As the associated works will be undertaken in the heart of the complex, there will be an unavoidable level of disruption to routine training and trialling activities. To enable the works to be completed in the shortest possible timeframe and to ensure the safety of track users, spectators and horses, the following restrictions will be applied throughout the construction period:
|
Day |
Morning |
Afternoon |
|
Mondays |
Sunrise to 7am |
No Access |
|
Tuesdays |
Sunrise to 7am |
5pm to 7pm |
|
Wednesdays |
Sunrise to 7am |
No Access |
|
Thursdays |
Sunrise to 7am |
5pm to 7pm |
|
Fridays |
Sunrise to 7am |
No Access |
|
Saturdays |
Sunrise to 4pm |
|
|
Sundays (10/01/10 & 17/01/10) |
NO ACCESS |
|
Please note:
Whilst the works will create a short-term inconvenience to some track users, the longer term benefits of such improvements will be both significant and enduring. To this end, RWWA anticipates your cooperation and tolerance throughout the works period.
On a personal note, I would like to take this opportunity to thank all track users for their cooperation and good will throughout the year and to wish you and your families a very merry Christmas and prosperous New Year.
Regards
Dudley Corbett
Racing Training Centre Manager